Search results

1 – 2 of 2
Open Access
Article
Publication date: 17 May 2022

Micael Thunberg and Anna Fredriksson

The purpose of this study is to identify how the responsibilities and costs of planning, controlling and executing the material, resource and waste flows are shifted between…

1002

Abstract

Purpose

The purpose of this study is to identify how the responsibilities and costs of planning, controlling and executing the material, resource and waste flows are shifted between actors when introducing a construction logistics setup (CLS) as a product innovation in a construction project, compared to the traditional way of organizing these activities.

Design/methodology/approach

This study is an analytical conceptual research study which aims to bring new insights into a problem through logical relationship building. Empirical data are gathered in two cases where CLSs are used, through observations and interviews regarding how the activities within the order-to-delivery process are performed. The results have been discussed at workshops with suppliers, installation companies, contractor firms and trade unions.

Findings

The outcome of this study is a model for illustrating how costs and responsibilities are shifted in the construction project and supply chain when a CLS is introduced. The cost shift is dependent on the activity shift that accompanies the services included in the setup.

Practical implications

The practical contribution of this work is twofold. First, this study provides a methodology of how to evaluate the impact of logistics services on the actors in the construction project. Second, this study shows shifts in costs and responsibilities in logistics activities with the introduction of construction logistics services.

Originality/value

The theoretical contributions of the model and this study lie in the inclusion of a multi-actor perspective in total cost modelling in supply chains.

Details

Construction Innovation , vol. 23 no. 4
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 3 January 2017

Micael Thunberg, Martin Rudberg and Tina Karrbom Gustavsson

This study aims to identify and categorise common on-site problems from a supply chain management (SCM) perspective and to trace the origin of these problems in the construction…

3627

Abstract

Purpose

This study aims to identify and categorise common on-site problems from a supply chain management (SCM) perspective and to trace the origin of these problems in the construction project process, the supply chain or in the intersection between these processes. This allows for identification of how on-site problems affect SCM in construction projects and how they can be mitigated.

Design/methodology/approach

A literature review in combination with semi-structured interviews was used to identify on-site problems. This enabled triangulation and strengthened both construct validity and internal validity.

Findings

On-site problems can be categorised in one of the four following categories: material flows, internal communication, external communication or complexity. The first category has its origin in the supply chain, the second in the construction project process, the third in the supply chain-construction process intersection on site and the fourth in the construction project as a whole. The findings conclude that on-site problems often originate from construction companies’ lack of supply chain orientation.

Research limitations/implications

It is suggested that supply chain planning (SCP) can facilitate on-site problem mitigation in construction project management. This extends the body of knowledge of SCP in construction project management and supports the development of effective on-site construction project management.

Practical implications

The results show that SCP can aid construction project management in handling on-site problems earlier in the project process.

Originality/value

The main value lies in extending the body of knowledge in construction project management research by applying an SCM perspective and by introducing SCP to support more effective construction project management.

Details

Construction Innovation, vol. 17 no. 1
Type: Research Article
ISSN: 1471-4175

Keywords

1 – 2 of 2